Proposition 12 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 101202025 TxDOT District Dallas County Name Collin Funding Status Funded
Highway FM 545 Project Length .123 Miles Project Type Proposition 12 Bid Date 2011-May
Work From AT SISTER GROVE CREEK Low Bid Amount $2,728,999.99
Work To .
Description REPLACE BRIDGE
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Mo Bur, P.E. Phone: (214) 320-6281
Construction Company ED BELL CONSTRUCTION COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/27/2011 08/10/2012 208 200 96.15 % 87.50 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $125,823.48 $504,696.53
Construction $2,514,960.71 $3,220,174.19
Construction EngineeringConstruction Engineering Definition $128,391.31 $132,158.03
Contingency Contingency Definition $166,908.70
Indirect Indirect Definition $124,539.57
Total Cost $3,060,623.77 $3,857,028.75