Proposition 12 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
091512224 |
TxDOT District |
San Antonio |
County Name |
Bexar |
Funding Status |
Funded |
| Highway |
MH |
Project Length |
1.499 Miles |
Project Type |
Proposition 12 |
Bid Date |
2010-Aug |
| Work From |
WURZBACH PARKWAY ON NEW LOCATION |
Low Bid Amount |
$26,448,884.47 |
| Work To |
FROM FM 2696 TO WEST AVE |
| Description |
CONSTRUCT NEW ROAD |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gregg Granato, P.E. |
Phone: |
(210) 615-6049 |
| Construction Company |
LIBERTY MUTUAL INSURANCE COMPANY |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
05/2009 |
05/2009 |
07/2009 |
10/2009 |
11/2009 |
11/2009 |
10/2009 |
11/2009 |
| Actual Date |
05/2009 |
05/2009 |
07/2009 |
02/2010 |
04/2010 |
02/2010 |
04/2010 |
02/2010 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/07/2010 |
01/04/2011 |
273 |
603 |
128.30 % |
89.71 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$3,168,561.21 |
$3,486,429.60 |
| Construction |
$28,245,996.54 |
$24,001,100.58 |
Construction Engineering |
$2,909,903.15 |
$1,146,705.77 |
Contingency
 |
$5,819,806.30 |
|
Indirect
 |
$2,766,771.13 |
|
| Total Cost |
$42,911,038.33 |
$28,634,235.95 |
|
 |