Proposition 12 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
071801052 |
TxDOT District |
Dallas |
County Name |
Denton |
Funding Status |
Funded |
| Highway |
FM 156 |
Project Length |
4.682 Miles |
Project Type |
Proposition 12 |
Bid Date |
2010-Dec |
| Work From |
0.1 MI N OF FM 2450 |
Low Bid Amount |
$4,152,523.54 |
| Work To |
IH 35 |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Mo Bur, P.E. |
Phone: |
(214) 320-6281 |
| Construction Company |
JAGOE-PUBLIC COMPANY |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2010 |
08/2010 |
08/2010 |
08/2010 |
08/2010 |
08/2010 |
08/2010 |
08/2010 |
| Actual Date |
01/2008 |
04/2008 |
11/2010 |
11/2010 |
03/2005 |
09/2010 |
09/2010 |
11/2010 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 01/11/2011 |
04/20/2011 |
175 |
175 |
83.33 % |
96.49 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$203,473.65 |
$97,396.58 |
| Construction |
$6,016,416.10 |
$4,673,691.33 |
Construction Engineering |
$207,626.18 |
$167,494.82 |
Contingency
 |
$269,914.03 |
|
Indirect
 |
$201,397.39 |
|
| Total Cost |
$6,898,827.35 |
$4,938,582.73 |
|
 |