Proposition 12 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
050003462 |
TxDOT District |
Houston |
County Name |
Harris |
Funding Status |
Funded |
| Highway |
IH 45 |
Project Length |
1.679 Miles |
Project Type |
Proposition 12 |
Bid Date |
2011-May |
| Work From |
NYACK ROAD |
Low Bid Amount |
$77,483,150.84 |
| Work To |
0.7881 MILES SOUTH OF FM 1959 |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bill Brudnick, P.E. |
Phone: |
(713) 802-5617 |
| Construction Company |
WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2009 |
12/2009 |
07/2010 |
01/2011 |
08/2009 |
01/2011 |
11/2010 |
01/2011 |
| Actual Date |
08/2009 |
03/2010 |
07/2010 |
02/2011 |
|
|
|
02/2011 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 06/15/2011 |
06/17/2011 |
1,135 |
464 |
40.00 % |
43.31 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$3,630,308.14 |
$6,331,288.57 |
| Construction |
$88,166,945.55 |
$36,563,340.93 |
Construction Engineering |
$4,092,155.61 |
$1,586,772.43 |
Contingency
 |
$8,184,311.22 |
|
Indirect
 |
$4,796,006.37 |
|
| Total Cost |
$108,869,726.89 |
$44,481,401.93 |
|
 |