Proposition 12 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 031401074 TxDOT District Fort Worth County Name Parker Funding Status Funded
Highway IH 20 Project Length 7.547 Miles Project Type Proposition 12 Bid Date 2010-Aug
Work From 0.4 MILE WEST OF FM 113 Low Bid Amount $23,651,493.12
Work To SPUR 312
Description REPAIR ROADWAY
Show Project Location
Contact Information
TxDOT Contact Scot D. Smith, P.E. Phone: (817) 370-6673
Construction Company W.W. WEBBER, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/14/2010 03/14/2011 325 349 101.45 % 96.19 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,158,923.16 $283,649.57
Construction $26,913,963.48 $24,574,456.97
Construction EngineeringConstruction Engineering Definition $1,064,317.19 $663,064.70
Contingency Contingency Definition $1,537,347.05
Indirect Indirect Definition $1,487,678.92
Total Cost $32,162,229.80 $25,521,171.24