Proposition 12 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 027114213 TxDOT District Houston County Name Harris Funding Status Funded
Highway IH 610 Project Length .198 Miles Project Type Proposition 12 District Est. Bid Date 2013-Aug
Work From W OF W 34TH ST ON US 290 (SEG 3)
Work To ON IH 610
Description CONSTRUCT INTERCHANGE DIRECT CONNECTION
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 01/2003 06/2009 04/2010 06/2011 08/2010 06/2011 05/2011 06/2011
Actual Date 01/2003 06/2009 02/2010 05/2013 08/2010 05/2013 05/2013 05/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $4,976,156.10 $4,719,451.76
Construction $130,951,476.44 $0.00
Construction EngineeringConstruction Engineering Definition $5,238,059.06 $0.00
Contingency Contingency Definition $7,857,088.59
Indirect Indirect Definition $6,194,004.84
Total Cost $155,216,785.03 $4,719,451.76