Proposition 12 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
027114213 |
TxDOT District |
Houston |
County Name |
Harris |
Funding Status |
Funded |
| Highway |
IH 610 |
Project Length |
.198 Miles |
Project Type |
Proposition 12 |
District Est. Bid Date |
2013-Aug |
| Work From |
W OF W 34TH ST ON US 290 (SEG 3) |
|
|
| Work To |
ON IH 610 |
| Description |
CONSTRUCT INTERCHANGE DIRECT CONNECTION |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bill Brudnick, P.E. |
Phone: |
(713) 802-5617 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
01/2003 |
06/2009 |
04/2010 |
06/2011 |
08/2010 |
06/2011 |
05/2011 |
06/2011 |
| Actual Date |
01/2003 |
06/2009 |
02/2010 |
05/2013 |
08/2010 |
05/2013 |
05/2013 |
05/2013 |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$4,976,156.10 |
$4,719,451.76 |
| Construction |
$130,951,476.44 |
$0.00 |
Construction Engineering |
$5,238,059.06 |
$0.00 |
Contingency
 |
$7,857,088.59 |
|
Indirect
 |
$6,194,004.84 |
|
| Total Cost |
$155,216,785.03 |
$4,719,451.76 |
|
 |