Proposition 12 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
016204047 |
TxDOT District |
Dallas |
County Name |
Navarro |
Funding Status |
Funded |
| Highway |
SH 31 |
Project Length |
.938 Miles |
Project Type |
Proposition 12 |
Bid Date |
2010-Aug |
| Work From |
28TH STREET |
Low Bid Amount |
$9,138,952.52 |
| Work To |
15TH ST IN THE CITY OF CORSICANA |
| Description |
REPAIR ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Mo Bur, P.E. |
Phone: |
(214) 320-6281 |
| Construction Company |
LONE STAR CIVIL CONSTRUCTION, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
07/2006 |
10/2007 |
11/2008 |
11/2009 |
12/2009 |
11/2009 |
04/2009 |
12/2009 |
| Actual Date |
07/2006 |
10/2007 |
11/2008 |
05/2010 |
06/2010 |
03/2010 |
03/2010 |
06/2010 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 09/14/2010 |
07/22/2011 |
532 |
478 |
79.01 % |
55.42 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$467,453.78 |
$1,492,810.50 |
| Construction |
$8,849,756.66 |
$5,258,663.69 |
Construction Engineering |
$476,993.65 |
$640,737.96 |
Contingency
 |
$620,091.75 |
|
Indirect
 |
$466,499.79 |
|
| Total Cost |
$10,880,795.63 |
$7,392,212.15 |
|
 |