Project ID 014602031 TxDOT District Childress County Name Cottle Funding Status Funded
Highway US 62 Project Length 12.629 Miles Project Type Proposition 12 v2 Bid Date 2012-Jul
Work From MOTLEY C/L, E Low Bid Amount $9,471,259.09
Work To PADUCAH WCLL
Description RESURFACE ROADWAY
Show Project Location
Contact Information
TxDOT Contact Chuck Steed, P.E. Phone: (940)-937-7191
Construction Company DUININCK, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/17/2012 06/24/2013 211 147 69.67 % 99.92 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $464,091.70 $46,722.52
Construction $8,482,905.08 $10,023,067.73
Construction EngineeringConstruction Engineering Definition $340,731.33 $208,613.63
Contingency Contingency Definition $152,420.57
Indirect Indirect Definition $1,266,307.34
Total Cost $10,706,456.02 $10,278,403.88