Proposition 12 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 007908003 TxDOT District Fort Worth County Name Erath Funding Status Funded
Highway US 67 Project Length 2.790 Miles Project Type Proposition 12 v2 Bid Date 2013-Aug
Work From 1.75 MI N OF COMANCHE COUNTY LINE Low Bid Amount $12,608,803.64
Work To SH 6
Description CONSTRUCT NEW ROAD
Show Project Location
Contact Information
TxDOT Contact Scot D. Smith, P.E. Phone: (817) 370-6673
Construction Company PRATER EQUIPMENT CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/24/2013 01/06/2014 380 228 60.00 % 37.51 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $617,831.38 $324,406.80
Construction $12,795,046.40 $4,868,350.65
Construction EngineeringConstruction Engineering Definition $576,222.33 $163,766.54
Contingency Contingency Definition $1,044,008.94
Indirect Indirect Definition $540,917.68
Total Cost $15,574,026.73 $5,356,523.99