Proposition 12 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 005008086 TxDOT District Houston County Name Harris Funding Status Funded
Highway US 290 Project Length 2.576 Miles Project Type Proposition 12 Bid Date 2013-Mar
Work From WEST OF ELDRIDGE PARKWAY Low Bid Amount $57,979,154.72
Work To WEST OF FM 529 (SEGMENT 7)
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Construction Company WEBBER, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/17/2013 09/04/2013 645 121 18.76 % 9.16 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $2,840,978.58 $9,832,255.43
Construction $63,248,432.59 $5,589,231.59
Construction EngineeringConstruction Engineering Definition $2,319,166.19 $265,341.25
Contingency Contingency Definition $3,478,749.28
Indirect Indirect Definition $2,742,414.02
Total Cost $74,629,740.66 $15,686,828.27