Proposition 12 Project Detail

Data updated on: 9/02/2014 11:01AM Print This Page
Project Summary
Project ID 003806040 TxDOT District Pharr County Name Starr Funding Status Funded
Highway US 83 Project Length 12.508 Miles Project Type Proposition 12 Bid Date 2011-Apr
Work From LOMA BLANCA RD Low Bid Amount $16,293,020.71
Work To ZAPATA STARR COUNTY LINE
Description REBUILD ROADWAY
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Construction Company LIBERTY MUTUAL INSURANCE COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
06/01/2011 08/15/2011 480 680 141.67 % 91.19 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $798,358.01 $424,463.58
Construction $17,385,598.54 $15,160,739.65
Construction EngineeringConstruction Engineering Definition $733,185.93 $609,010.10
Contingency Contingency Definition $1,059,046.35
Indirect Indirect Definition $1,119,330.52
Total Cost $21,095,519.35 $16,194,213.33