Proposition 12 Project Detail

Data updated on: 9/02/2014 11:01AM Print This Page
Project Summary
Project ID 003805035 TxDOT District Pharr County Name Zapata Funding Status Funded
Highway US 83 Project Length 6.023 Miles Project Type Proposition 12 Bid Date 2010-Sep
Work From 0.369 MILES NORTH OF FM 2687 Low Bid Amount $25,577,160.72
Work To 6.392 MILES NORTH OF 2687
Description REBUILD ROADWAY
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Construction Company ANDERSON COLUMBIA CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/20/2010 01/04/2011 480 685 137.00 % 99.39 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,256,964.84 $627,255.66
Construction $24,973,064.57 $28,045,705.58
Construction EngineeringConstruction Engineering Definition $1,154,355.46 $888,668.39
Contingency Contingency Definition $1,885,221.39
Indirect Indirect Definition $1,757,150.95
Total Cost $31,026,757.21 $29,561,629.63