Proposition 12 Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 001507065 TxDOT District Waco County Name Bell Funding Status Funded
Highway IH 35 Project Length 3.333 Miles Project Type Proposition 12 Bid Date 2011-Jul
Work From FM 2843 Low Bid Amount $70,449,357.09
Work To FM 2484
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company JAMES CONSTRUCTION GROUP, L.L.C.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/30/2011 01/05/2012 920 711 77.28 % 50.45 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $3,425,205.33 $5,842,173.34
Construction $72,636,928.58 $36,254,856.87
Construction EngineeringConstruction Engineering Definition $3,145,596.73 $4,452,321.39
Contingency Contingency Definition $4,893,150.47
Indirect Indirect Definition $3,795,686.73
Total Cost $87,896,567.84 $46,549,351.60