Proposition 12 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
001504067 |
TxDOT District |
Waco |
County Name |
Bell |
Funding Status |
Funded |
| Highway |
IH 35 |
Project Length |
5.469 Miles |
Project Type |
Proposition 12 |
Bid Date |
2011-Jun |
| Work From |
NORTH LP 363 |
Low Bid Amount |
$123,628,672.32 |
| Work To |
N OF TROY |
| Description |
CONSTRUCT NEW ROADWAY LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Andy Petter, P.E. |
Phone: |
(254) 867-2740 |
| Construction Company |
JAMES CONSTRUCTION GROUP, L.L.C. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
01/2010 |
05/2010 |
10/2010 |
05/2011 |
05/2010 |
05/2011 |
05/2011 |
06/2011 |
| Actual Date |
01/2010 |
06/2010 |
11/2010 |
05/2011 |
11/2010 |
05/2011 |
05/2011 |
05/2011 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 07/22/2011 |
03/12/2012 |
1,166 |
334 |
28.64 % |
24.53 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$6,345,517.87 |
$8,386,596.79 |
| Construction |
$138,380,621.55 |
$30,611,704.67 |
Construction Engineering |
$5,827,516.41 |
$1,257,615.23 |
Contingency
 |
$9,065,025.52 |
|
Indirect
 |
$7,031,869.80 |
|
| Total Cost |
$166,650,551.15 |
$40,255,916.69 |
|
 |