Proposition 12 Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 001408075 TxDOT District Waco County Name McLennan Funding Status Funded
Highway IH 35 Project Length 7.657 Miles Project Type Proposition 12 Bid Date 2010-Jul
Work From HILLTOP RD Low Bid Amount $166,787,859.79
Work To FM 1858 IN WEST
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company WILLIAMS BROTHERS CONSTRUCTION CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/24/2010 10/22/2010 1,220 1,166 81.77 % 88.11 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $8,450,043.23 $4,197,887.35
Construction $180,539,828.83 $159,971,374.37
Construction EngineeringConstruction Engineering Definition $7,760,243.79 $5,407,818.92
Contingency Contingency Definition $12,071,490.33
Indirect Indirect Definition $13,468,334.21
Total Cost $222,289,940.39 $169,577,080.64