Proposition 12 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
001408075 |
TxDOT District |
Waco |
County Name |
McLennan |
Funding Status |
Funded |
| Highway |
IH 35 |
Project Length |
7.657 Miles |
Project Type |
Proposition 12 |
Bid Date |
2010-Jul |
| Work From |
HILLTOP RD |
Low Bid Amount |
$166,787,859.79 |
| Work To |
FM 1858 IN WEST |
| Description |
CONSTRUCT NEW ROADWAY LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Andy Petter, P.E. |
Phone: |
(254) 867-2740 |
| Construction Company |
WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
02/2009 |
06/2009 |
10/2009 |
01/2010 |
02/2009 |
01/2010 |
01/2010 |
01/2010 |
| Actual Date |
02/2009 |
06/2009 |
10/2009 |
01/2010 |
02/2009 |
01/2010 |
01/2010 |
01/2010 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/24/2010 |
10/22/2010 |
1,220 |
737 |
60.26 % |
66.32 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$8,450,043.23 |
$4,179,446.15 |
| Construction |
$180,539,828.83 |
$116,343,616.03 |
Construction Engineering |
$7,760,243.79 |
$3,488,375.91 |
Contingency
 |
$12,071,490.33 |
|
Indirect
 |
$13,468,334.21 |
|
| Total Cost |
$222,289,940.39 |
$124,011,438.09 |
|
 |