Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 091271895 TxDOT District Houston County Name Harris Funding Status Funded
Highway CR Project Length .665 Miles Project Type Traditional Bid Date 2012-Nov
Work From W GREENS RD FRM SH249(700'W HCFCD) Low Bid Amount $7,785,990.84
Work To CUTTEN RD
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Pamela Elmer, P.E. Phone: (713) 802-5646
Construction Company TEXAS STERLING CONSTRUCTION CO.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/04/2013 02/08/2013 261 258 98.85 % 99.43 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $371,465.51 $0.00
Construction $7,938,641.22 $8,440,860.05
Construction EngineeringConstruction Engineering Definition $371,465.51 $267,758.27
Contingency Contingency Definition $94,761.61
Indirect Indirect Definition $368,277.36
Total Cost $9,144,611.21 $8,708,618.32