Amount Paid to Date Breakdown - Project 348701004
| Construction | |
| Expenditure Description (Code) | Amount Paid to Date |
| DIST INDIRECT COSTS (NOT BILLABLE TO FHWA) | $1,064,925.43 |
| DISTRICT INDIRECT COSTS (BILLABLE TO FHWA) | $306.73 |
| DIV INDIRECT COSTS(NOT BILLABLE TO FHWA) | $1,632,288.63 |
| DIVISION INDIRECT COSTS (BILLABLE TO FHWA) | $396.55 |
| PAYMENTS FOR ALL OUTSIDE FORCEACCOUNT WORK (7347) | $11,611.86 |
| PAYMENTS TO CONTRACTORS, INCL CDA PAYMENTS (7347) | $40,146,786.32 |
| RETAINAGE HELD IN STATE TREASURY (7347) | $64,149.26 |