Amount Paid to Date Breakdown - Project 054206041

Construction
Expenditure Description (Code) Amount Paid to Date
DIST INDIRECT COSTS (NOT BILLABLE TO FHWA) $552,080.13
DISTRICT INDIRECT COSTS (BILLABLE TO FHWA) $9,807.28
DIV INDIRECT COSTS(NOT BILLABLE TO FHWA) $636,983.91
DIVISION INDIRECT COSTS (BILLABLE TO FHWA) $11,362.17
LIQUIDATED DAMAGES (7347) $365,800.00
PAYMENTS FOR ALL OUTSIDE FORCEACCOUNT WORK (7347) $274,422.17
PAYMENTS TO CONTRACTORS, INCL CDA PAYMENTS (7347) $16,199,969.44