Amount Paid to Date Breakdown - Project 050003462
| Construction | |
| Expenditure Description (Code) | Amount Paid to Date |
| DIST INDIRECT COSTS (NOT BILLABLE TO FHWA) | $716,607.18 |
| DIV INDIRECT COSTS(NOT BILLABLE TO FHWA) | $1,222,403.38 |
| FUND TRANSFERS FOR CONSTRUCTN EXPENDITURES (7397) | NaN |
| HAZARDOUS/TOXIC WASTE DISPOSAL (7272) | $30,751.75 |
| LABORERS, DO NOT USE FOR CDA PAYMENTS (7299) | $3,009.15 |
| PAYMENTS TO CONTRACTORS, INCL CDA PAYMENTS (7347) | $34,589,144.41 |
| STEEL, STRUCTURAL (7328) | $1,425.06 |