Amount Paid to Date Breakdown - Project 020202015

Construction
Expenditure Description (Code) Amount Paid to Date
DIST INDIRECT COSTS (NOT BILLABLE TO FHWA) $45,703.03
DIV INDIRECT COSTS(NOT BILLABLE TO FHWA) $63,506.64
LIQUIDATED DAMAGES (7347) $44,375.00
PAYMENTS TO CONTRACTORS, INCL CDA PAYMENTS (7347) $1,684,107.56