Amount Paid to Date Breakdown - Project 011313106

Construction
Expenditure Description (Code) Amount Paid to Date
DIST INDIRECT COSTS (NOT BILLABLE TO FHWA) $985,185.43
DIV INDIRECT COSTS(NOT BILLABLE TO FHWA) $1,122,375.56
PAYMENTS TO CONTRACTORS, INCL CDA PAYMENTS (7347) $29,114,477.97