Amount Paid to Date Breakdown - Project 001407083

Construction
Expenditure Description (Code) Amount Paid to Date
DIST INDIRECT COSTS (NOT BILLABLE TO FHWA) $608,236.95
DISTRICT INDIRECT COSTS (BILLABLE TO FHWA) $236.88
DIV INDIRECT COSTS(NOT BILLABLE TO FHWA) $1,295,035.79
DIVISION INDIRECT COSTS (BILLABLE TO FHWA) $528.75
ITS EQUIPMENT, CAPITALIZED (=>$5,000) (7328) $187,160.00
PAYMENTS TO CONTRACTORS, INCL CDA PAYMENTS (7347) $32,257,051.76
PROMOTIONAL ITEMS (7309) $34.56