San Antonio District Letting Performance (FY 2008) |
12 Month Projected Letting Schedule = $251.19 Million
12 Month Actual Letting Amount = $223.45 Million
|
|
| Backlog Amounts (in Millions) |
| Sept |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Apr |
May |
June |
July |
Aug |
| $0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$1.91 |
$1.91 |
$3.69 |
$0.00 |
$0.00 |
$25.77 |
|

Revised Schedule - The revised schedule line represents the original 2008 12 Month Letting Schedule minus delayed mobility projects (scheduled February - August) per Administration Direction.
Updated after the August 2008 Letting |